construction claimsIn Lodge Construction, Inc. v. United States, the US Court of Federal Claims (“COFC”) prefaced its 46-page opinion by stating: “This case should serve as a cautionary tale to government contractors.”[1] Our ears perk up any time we read that kind of admonition in a published decision. The Lodge holding is, indeed, loaded with lessons on what to do, and what not to do, when presenting Contract Disputes Act (“CDA”) claims to the government. In particular, federal construction contractors and their performance bond sureties should take heed of the court’s holding in this highly-illustrative fraud case.

Background of the case

In 2010, the Army Corps of Engineers (“Government”) awarded Lodge Construction (“Lodge”) a fixed-price contract to rehabilitate a levee in Florida. To accommodate subsurface work, Lodge designed and constructed a temporary cofferdam based on a geotechnical site inspection and analysis furnished by the Government. The Government accepted Lodge’s final cofferdam design in July 2011. In March 2012, however, water breached two sections of the cofferdam’s sheet pile wall, after which the Government retroactively disapproved of Lodge’s cofferdam design. The Government requested that Lodge submit a new sheet pile design by May 29, 2012.
Continue Reading Fraud and Forfeiture: Cautionary Tales of a Construction Claim Gone Wrong

While most federal contractors are eminently familiar with the False Claims Act (“FCA”)—government’s most potent weapons for prosecuting false claims—the anti-fraud provision of the Contract Disputes Act (“CDA”) does not receive nearly as much attention in the headlines. CDA anti-fraud cases are rarer than FCA cases for a couple reasons. First, the government’s remedies under the CDA pale in comparison to the robust deterrents available under the FCA, which include five-figure fines (between $11,000 and $22,000 per claim) and potential treble damages.[1] Second, the government is limited to enforcing FCA fraud claims in the federal court system, which complicates matters when the government seeks to assert FCA counterclaims as leverage in cases pending in the Civilian Board of Contract Appeals or the Armed Services Board of Contract Appeals.[2]  Thus, case law addressing CDA anti-fraud claims is sparse; indeed the US Court of Appeals for the Federal Circuit has never issued a published opinion discussing such claims. Last month, however, emerged an anti-fraud decision in the US Court of Federal Claims (“COFC”) that may eventually find itself worthy of higher-level scrutiny.
Continue Reading US Court of Federal Claims Clarifies the Statute of Limitations for CDA Anti-Fraud Claims

The Contract Disputes Act presents government contractors with two venue options for appealing an adverse final decision.[1]  Within one year of receiving a denial of its claim, the contractor may appeal to the United States Court of Federal Claims (COFC) or, in the alternative, the contractor has ninety days to appeal to an administrative law judge in the appropriate agency board of contract appeals.  For defense contractors, that means the Armed Services Board of Contract Appeals; and with a few exceptions, non-defense contractors may appeal to the Civilian Board of Contract Appeals (CBCA).[2]
Continue Reading Hof Construction: The CBCA Decides How it Will Address Conflicting Decisions of Predecessor Agency