By April 18, 2026, New York construction litigation will operate on a faster—and far less forgiving—timeline. The Avoiding Vexatious Overuse of Impleading to Delay (the “AVOID Act”), signed into law on December 19, 2025, fundamentally rewrites third‑party practice under CPLR § 1007 by imposing strict deadlines to bring subcontractors, suppliers, and other responsible parties into a case.
Continue Reading The AVOID Act: A New Timeline for Liability in New York Construction Projects
The indemnity clause is one of the most scrutinized, negotiated, and litigated terms of any construction contract. The indemnity clause is a risk-shifting provision that requires the contractor to defend, reimburse, and “hold harmless” the owner and architect from claims and liability “arising out of” the contractor’s work. The indemnity clause is focused on bodily injury and property damage suffered by third parties seeking recompense against the owner. Indemnity clauses share the same core purpose, but can have varying reach, depending on the language used.